Skip to main content
Beta! Dokumentasjonen er automatisk generert. Informasjonen kan være ufullstendig og inneholde feil, spesielt skjermbilder og videoer. Se Om hjelpesidene. Vi vil veldig gjerne ha innspill: Kontakt oss via «Fant du det du lette etter?» nederst, i chatten nede til høyre eller på support@placepoint.no – vi svarer så fort vi kan!

Grid connection queue

Capacity in the transmission grid that is tied up in Statnett's connection cases, aggregated per substation. The dataset shows how much capacity is reserved or queued at each point, how many cases compete for the same substation, the largest single case and the next planned connection. The position of the substations comes from NVE's grid installations.

Statnett distinguishes between cases that are requested, reserved, placed in a capacity queue and connected. The queue contains only customers that are mature enough to take a place, and a project that has been granted capacity on special terms also sits in the ordinary queue.

For a developer, this is an early-stage filter for power-intensive projects such as data centres, battery factories and electrified industry. A site can be zoned and available, and still be unsuitable because the capacity at the nearest substation is already tied up. The dataset also shows who competes for the same point, and which industries they belong to. Part of Placepoint's map layer for energy. Related: Grid installations, Planned Electrical Installations in the Power System, Substations, towers, poles & licences.

The point on the map is the substation, not the project site. Statnett registers the cases manually from 2018 onwards, so gaps can occur.

Update frequency: Daily.

Source: Statnett, position from NVE's grid installations.

How the dataset appears on the map

The dataset is part of the Energy map layer. Each circle is a substation. The size follows the tied-up capacity in MW, and the color shows what the substation has most of:

ColorMeaning
RedBoth queue and reservations at the same substation
OrangeCases in the queue
YellowReserved capacity
BlueConnected cases only
GreyHistory, everything has been withdrawn

Grid connection queue in Placepoint

Click a substation to see the tied-up capacity split by queued, reserved, connected and withdrawn, the number of cases, the industry types competing, the largest single case with customer, the next planned connection, the price area and the county.

Beta! Dokumentasjonen er automatisk generert. Informasjonen kan være ufullstendig og inneholde feil, spesielt skjermbilder og videoer. Se Om hjelpesidene. Vi vil veldig gjerne ha innspill: Kontakt oss via «Fant du det du lette etter?» nederst, i chatten nede til høyre eller på support@placepoint.no – vi svarer så fort vi kan!